Upper Sindh II

1. Year of commissioning 1973-74
2. Installed capacity 2x 1.30MW = 22.6MW
3. Present derated capacity 14MW
4. Head 149 M
5. Length of water Conductor 11 KM
6. Design discharge capacity 425 cusecs