Project Installed Capacity in MW Status Awarded To
PHASE-I PROJECTS

Athwatoo

10

Commissioned.

M/s Magpie & Co.

 Tangmarg

10

Commissioned.

M/s Magpie & Co.

Ranjala Dunadi

15

Commissioned.

M/s Choudhary Power Projects Limited

Brenwar

7.5

Commissioned.

M/s P&R Engineering

Mandi

12.5

Commissioned.

M/s Magpie Hydel Constructions

Kahmil

4

Contract Terminated due to poor perforamce by Developer(2017-18)

M/s Rehbar Engineering Ltd.

Boniyar

12

Work in progress

M/s VRB Hydro Power

Chandanwari

7

DPR under preparation

M/s Nazir Hussain Khan

Drung

5

Land Acquisition clearance in Progress.

M/s Chenab Valley Leasing Company.

Aharbal

22.5

Project Site surrendered due to Tourism and Enviornmental issues.

M/s JAL

PHASE-II PROJECTS

Ans-I

40

In 2012 Implementation agreement was signed and DPR was under prepration.However, the IPP has communicated that the project as a single stage 40MW capacity was not ecnomically viable and requested that the project be splitted into two stages 20MW each to achieve viability.

M/s Sri-Awantika Consortium

Girjan Ki Gali

12

DPR under preparation

M/s Raheja Power Ventures Pvt. Ltd.

Patnazi-Bunjwa

21

TEC accorded to DPR

M/s Patnazi Power (Energo Group)

PHASE-III PROJECTS

Gulabgarh

6.50

Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV.

M/s Boom Systems Pvt. Ltd.

Nihama

6

Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV

M/s Millde East Recycling Company WILL.

Shunahkag

9

Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV

M/s Boom Systems Pvt. Ltd.

Sultanphatri

3

DPR under preparation

M/s SRM Contractors Pvt. Ltd.

Shranz
Baramullah

10

Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV.

M/s Trumboo Cement Industries pvt. Ltd.

Tamasha

9

Bidder Didnot pay upfront Premium.LOA Withdrawn. (Project is being implemented under PMDP-2015)

M/s Trumboo Cement Industries pvt. Ltd.

Bairaas

9

Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV

M/s Trumboo Cement Industries pvt. Ltd.

Chenani-IV

7

Non Responsive Bid.

Sewa-I

8

Non Responsive Bid

Mawar

10

Non Responsive Bid

Erin

10

No Response.

Boniyar

6

No Response.

Phagla

16

No Response. (Project is being implemented under PMDP-2015)

Bringi

4

No Response.

Shaliganga

4.5

No Response.

Hanswar

6

No Response.

Upper Ans-I

5.5

No Response.

Chingus-I

3

No Response.

Chingus-II

3

No Response.

Kutimarg

7.25

No Response.

Pumbai Aridajan

4

No Response.

Kutbal

4

No Response.

Thanamandi

2.75

No Response.

Rongdo

9

No Response.