Project | Installed Capacity in MW | Status | Awarded To | PHASE-I PROJECTS |
---|---|---|---|
10 |
Commissioned. |
M/s Magpie & Co. |
|
10 |
Commissioned. |
M/s Magpie & Co. |
|
15 |
Commissioned. |
M/s Choudhary Power Projects Limited |
|
7.5 |
Commissioned. |
M/s P&R Engineering |
|
12.5 |
Commissioned. |
M/s Magpie Hydel Constructions |
|
4 |
Contract Terminated due to poor perforamce by Developer(2017-18) |
M/s Rehbar Engineering Ltd. |
|
12 |
Work in progress |
M/s VRB Hydro Power |
|
5 |
Land Acquisition clearance in Progress. |
M/s Chenab Valley Leasing Company. |
|
22.5 |
Project Site surrendered due to Tourism and Enviornmental issues. |
M/s JAL |
PHASE-II PROJECTS |
40 |
In 2012 Implementation agreement was signed and DPR was under prepration.However, the IPP has communicated that the project as a single stage 40MW capacity was not ecnomically viable and requested that the project be splitted into two stages 20MW each to achieve viability. |
M/s Sri-Awantika Consortium |
|
12 |
DPR under preparation |
M/s Raheja Power Ventures Pvt. Ltd. |
|
7 |
DPR under preparation |
M/s Nazir Hussain Khan |
|
21 |
TEC accorded to DPR |
M/s Patnazi Power (Energo Group) |
PHASE-III PROJECTS |
Gulabgarh |
6.50 |
Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV. |
M/s Boom Systems Pvt. Ltd. |
Nihama |
6 |
Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV |
M/s Millde East Recycling Company WILL. |
Shunahkag |
9 |
Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV |
M/s Boom Systems Pvt. Ltd. |
3 |
DPR under preparation |
M/s SRM Contractors Pvt. Ltd. |
|
Shranz |
10 |
Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV. |
M/s Trumboo Cement Industries pvt. Ltd. |
Tamasha |
9 |
Bidder Didnot pay upfront Premium.LOA Withdrawn. (Project is being implemented under PMDP-2015) |
M/s Trumboo Cement Industries pvt. Ltd. |
Bairaas |
9 |
Bidder Didnot pay upfront Premium.LOA Withdrawn,To be retendered under Phase-IV |
M/s Trumboo Cement Industries pvt. Ltd. |
Chenani-IV |
7 |
Non Responsive Bid. |
|
Sewa-I |
8 |
Non Responsive Bid |
|
Mawar |
10 |
Non Responsive Bid |
|
Erin |
10 |
No Response. |
|
Boniyar |
6 |
No Response. |
|
Phagla |
16 |
No Response. (Project is being implemented under PMDP-2015) |
|
Bringi |
4 |
No Response. |
|
Shaliganga |
4.5 |
No Response. |
|
Hanswar |
6 |
No Response. |
|
Upper Ans-I |
5.5 |
No Response. |
|
Chingus-I |
3 |
No Response. |
|
Chingus-II |
3 |
No Response. |
|
Kutimarg |
7.25 |
No Response. |
|
Pumbai Aridajan |
4 |
No Response. |
|
Kutbal |
4 |
No Response. |
|
Thanamandi |
2.75 |
No Response. |
|
Rongdo |
9 |
No Response. |