Chenani II
| 1. |
Year of commissioning |
1996 |
| 2. |
Installed capacity |
2 X 1 =2 MW |
| 3. |
Location |
|
|
District |
Udhampur |
|
Stage-II |
Latitude 32 Deg-55'N Longitude 75 Deg-09 E |
| 5 |
Hydrology and climate
condition |
|
|
River |
Tawi |
|
Catchment area upto power
house stage-I |
652 Sq. Km |
| 6. |
Water Conductor System |
|
|
Total Length |
2.315 Kms |
|
Carrying Capacity |
7.12 cumecs |
| 7. |
Penstock |
|
|
Feeder Penstock |
50 M |
|
Diameter |
2600 mm. |
|
Bifercation |
|
|
No. of pipes |
2 |
|
Length of each pipe |
18 Mt. |
|
Diameter of each pipe |
1900m |
| 8. |
Power House |
|
|
Location |
Upstream of Salmey Acqueduct
on left bank of river tawi |
|
Installed Capacity |
2 Units of 1 MW each |
|
Type |
Surface |
|
Size |
26m x 11.4 m |
|
No. of Units |
2 No.s |
|
Gross Head |
32.50 |
|
Net head |
32.50 |
|
Type of turbine |
Francis |
|
Rated output |
1 MW |
| 9 |
Generator |
|
|
No. and type |
2 x 1000 Kw |
|
Generating Volt. |
415 V |
|